Project Management Case Study

Project Management Case Study

Case Study – Theatre Restoration
Originally opened in 1930, the Dundas Theatre in Nassau, The Bahamas is a celebrated home to encouraging and assisting the development of various cultural activities in the country. Over time the Dundas was in need of significant restoration and upgrade required to address its substantial functional deficiencies which made it inadequate to support newer performances. The upgrade required a change to sightlines, seating and flexibility in the delivery of the project to avoid impacting the operation of key annual events, specifically the annual Ringplay Show for orphaned children.

The brief required an upgrade of all facilities to integrate back of house production, catering, artist change and warm-up, theatre infrastructure and technologies, commercially supportive facilities, hire-out function spaces and a cafe. The refurbishment needed to respect the heritage value of the original structure while rejuvenating its cultural life as one of Nassau’s traditional venues. Apart from the original structure, there was significant work done on the building. The new work extends the original footprint, mainly in creating new upper stories. Major areas for refurbishment included replacing the roof damaged by hurricanes through the years, mould remediation, strengthening the foundation and

refinishing all interior and exterior walls and replacing the stage and props. The entire ceiling was replaced with a new cladding system that improved acoustics in the theatre.

The work on this project was conducted so that the theatre remained open during most of the refurbishment.

1. How do you think the use of project management was able to facilitate this?

● Planning – tools, manpower, scheduling

● Gannt diagram – specify dates

● Used phases – smaller projects

2. What processes would have been necessary before the start of the project?

Plan –

Budget – Financial Support Team

Team Leader Timeline

Define deliverables Stakeholders

Risks & mitigation plans

 

3. Who would be the project stakeholders? Actors & Producers

Theatre goers Construction Companies

City regulators – construction laws Investors/financiers

Project Team PM

Architect Theatre owner Employees Suppliers

4. What was the project scope?

What is included and excluded from the project scope?

strengthening the foundation and refinishing all interior and exterior walls and

replacing the stage and props.

5. What were the project constraints? Must remain open during the work Budget

Time

Manpower – pm, team, suppliers, construction workers

Must retain original building structure for heritage – exterior cannot change

6. What worked well to complete this project?

 

The work was completed on time in various phases Effective & efficient planning

Deliverables were clearly defined Budget/time respected

Stakeholders were onboard and invested in the project


"Place your order now for a similar assignment and have exceptional work written by our team of experts, guaranteeing you A results."

Order Solution Now

Our Service Charter


1. Professional & Expert Writers: Eminence Papers only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed of papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided by Eminence Papers are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Eminence Papers are known for the timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit in all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Eminence Papers, we have put in place a team of experts who answer all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.